Start here: the question on your desk
When an engineer says an analyser is "ready", ask: ready for what? An installed analyser has power, water and software. It has not yet shown:
- that it is the item the laboratory ordered,
- that it arrived undamaged,
- that it works to its specification in our room, or
- that anyone has decided it may be used.
Method verification assumes all of that. If the equipment record cannot show it, the verification data rest on an instrument nobody has formally accepted. An assessor, or a colleague investigating a strange result two years later, will find a gap at the very start of the story.
This chapter treats the analyser as a piece of equipment with a life of its own:
ISO 15189:2022 sets the requirements for equipment in clause 6.4 and for the equipment record in clause 6.4.7. Clause 8.4.3 governs how long records are kept and how they are protected. This chapter explains what those requirements mean at the bench, in the order a laboratory meets them. The rest of the course deals with the examination methods that run on the equipment.
By the end of this chapter you should be able to
- Identify a new item of equipment uniquely and record what was received, in what condition and with which software.
- Record receipt, acceptance testing and entry into service as three separate milestones, each with its own evidence and date.
- Explain how accepting equipment differs from verifying or validating an examination method.
- Keep maintenance, fault, repair, modification and calibration records so that any change can be judged for its effect on equipment and methods.
- Show the current status of every item of equipment and retrieve its full history for as long as the records must be kept.
Map of this chapter
| # | Study section | Book section(s) | Printed pages |
|---|---|---|---|
| 1 | Start here: the question on your desk | Chapter 0 opening, learning objectives | 3–4 |
| 2 | Receive and identify the equipment | §0.1 (Table 0.1) | 4–5 |
| 3 | Accept it for service: milestones, criteria and authority | §0.2 (first part) | 6–7 |
| 4 | Equipment acceptance is not method verification | §0.2 (second part, Table 0.2) | 7–9 |
| 5 | Maintain it: the five kinds of record entry | §0.3 (first part) | 9–10 |
| 6 | A change can trigger two reviews; return to service | §0.3 (second part, Table 0.3) | 10–12 |
| 7 | Track its status and retain its history | §0.4 | 12–13 |
| 8 | Worked Example 0.1 (part 1): delivery, installation and a failed check | Worked Example 0.1, Steps 1–3 (Table 0.4) | 13–16 |
| 9 | Worked Example 0.1 (part 2): authorise, enter into service, record | Worked Example 0.1, Steps 4–5 (Tables 0.5, 0.6) | 16–19 |
| 10 | Reusable equipment-record template | Template (Table 0.7) | 20–21 |
| 11 | Worked Example 0.2: returning a repaired module to service | Worked Example 0.2 (Table 0.8) | 21–23 |
| 12 | Common errors | Common errors | 23 |
| 13 | Chapter 0 checklist and the next decision | Checklist; From readiness to evaluation; references | 24–25 |
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, opening and learning objectives, pp.3–4; How this book is organised, p.viii
0.1 Receive and identify the equipment
💡 Equipment, in the sense that matters here, is anything that can influence a result. ISO 15189:2022 is explicit that this includes the software of instruments and of the laboratory information system (LIS), and items such as sample transport systems (clause 6.4.1).
A chemistry analyser is the obvious case. The same record discipline applies to:
- a centrifuge used for every sample,
- a water purification unit that feeds the analyser,
- a pipette used to prepare calibrators,
- the middleware that decides which results are autoverified.
A unique identity in practice
Each item that can influence results needs its own identity and a place in the laboratory's equipment register (clause 6.4.2). The identity has to be unique in practice, not just in principle: two analysers of the same model in the same room must never be confused in a maintenance log, a QC chart or an investigation.
Serial number → links that ID to the manufacturer's records
Table 0.1 lists what the record should capture on the day the equipment arrives, and why each item matters later.
| Item | What to record | Why it matters later |
|---|---|---|
| Laboratory equipment ID | The ID from the laboratory's register, also shown on a label on the instrument | Links every QC result, maintenance entry and investigation to one physical item |
| Manufacturer and supplier | Manufacturer's name and model; supplier or distributor, with contact details for service | Recalls, field safety notices and service requests come through these routes |
| Serial number and modules | Serial number of the main unit and of separately serialised modules (for example an ion-selective electrode unit or a sample handler) | A module can be replaced on its own; the record must show which module produced which results |
| Software and firmware | Version of the instrument software, firmware of key modules, and middleware or interface versions where they affect results | A version change can alter calculations, flags or data transfer, and must be traceable to the date it happened |
| Location | Room and position, and any later move | Environment, power and water supply differ between locations; a move can need fresh acceptance |
| Condition on receipt | New, used or reconditioned; packaging and transit indicators; missing or damaged items | A used or reconditioned instrument carries a history the laboratory should ask for |
| Instructions for use | Which manufacturer's documents apply (title, version or date), and where staff find the current copy | Staff must work to the current version, and the record shows which version was current when |
| Documents received | Installation report, certificates, declarations of conformity, service contract reference | Evidence for acceptance and for later service decisions |
The two items that cause most trouble
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, §0.1 Receive and identify the equipment, pp.4–5
0.2 Accept it for service: milestones, criteria and authority
Three milestones, three dates
Receipt, acceptance testing and entry into service are different events, and the record keeps them apart. Merging them into one date, usually the day the engineer leaves, hides what was actually checked and when.
| Milestone | What it is | What is known on that date |
|---|---|---|
| 1. Receipt | The day the equipment arrives and is identified | Only what was delivered and the condition it arrived in |
| 2. Acceptance testing | The period in which the equipment is installed and checked against written acceptance criteria | Ends with a review of the evidence and a decision |
| 3. Entry into service | The date from which the equipment may be used for a defined purpose, authorised by a named person | It cannot come before the acceptance decision |
ISO 15189:2022 requires the laboratory to confirm that equipment meets specified acceptability criteria before it is placed in service, and again before it is returned to service after it has been out of use (clause 6.4.3). The same clause expects measuring equipment to be capable of the accuracy or measurement uncertainty that a valid result needs. This links acceptance forward to the method evaluation:
Acceptance criteria written before the checks
Acceptance criteria are written before the installation checks start, for the same reason that verification criteria are written before the first study sample (Chapter 5): a criterion chosen after the result tends to fit the result.
For a chemistry analyser the criteria usually come from three sources:
| Source | What it sets |
|---|---|
| Manufacturer's installation protocol and specifications | What the instrument must achieve: temperature control, photometer checks, pipetting checks, water quality and so on |
| The hospital's own requirements | Electrical safety and site services |
| The laboratory | Checks only it can define, such as correct transfer of results, units and flags to the laboratory information system |
Each criterion should be written so that a reviewer can tell from the evidence whether it was met.
| Cannot be checked | Can be checked |
|---|---|
| "Installation satisfactory" | "Every item of the manufacturer's installation checklist completed and passed, report signed by the service engineer" |
Where the manufacturer's specification provides a number, the record states the number and the observed value, not only "pass".
How the analyser will be operated
Acceptance also settles how the analyser will be operated. ISO 15189:2022 expects safeguards against adjustments that could invalidate results, operation only by trained, authorised and competent staff, and use as the manufacturer specifies unless the laboratory has validated something different (clause 6.4.4). It treats electrical safety, working emergency stops and the safe disposal of hazardous waste as part of keeping equipment in working order (clause 6.4.5).
1. Who holds which access level in the instrument software, so that a calibration factor, a reportable range or a rerun rule cannot be changed by whoever happens to be logged in;
2. Which operators have been trained and authorised;
3. The safety checks.
In Worked Example 0.1, criteria A-3 and A-8 cover safety, and the access levels and training records are entered in the equipment record (Table 0.5).
Who reviews and who authorises
🔥 KEY POINT: The engineer's installation report is evidence, not a decision. Someone in the laboratory reviews the evidence against the criteria and decides. The record names that person, the evidence reviewed, the decision and the date.
In most laboratories this is the section supervisor or a scientist authorised for equipment acceptance, with the laboratory director or their delegate authorising entry into service. What matters is that the authority to accept equipment is defined in advance and that the record shows it was used.
Conditions on an acceptance
| Situation | What happens |
|---|---|
| A non-critical item is still outstanding (for example a spare part on order) | Acceptance can carry a condition: the record states it, who owns it and by when it must be closed |
| A failed criterion that affects results | Not a condition: the equipment stays out of service until the item is corrected and rechecked |
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, §0.2 Accept it for service (Three milestones, three dates; Acceptance criteria written before the checks; Who reviews and who authorises), pp.6–7
0.2 Equipment acceptance is not method verification
Accepting the analyser and verifying the examination methods that run on it answer different questions, and both are needed. Table 0.2 sets them side by side.
| Question | Equipment acceptance (this chapter) | Method verification or validation (Chapters 1 to 20) |
|---|---|---|
| What is being judged? | The instrument as a physical and software system | Each examination procedure: reagent, calibrator, instrument and method together |
| What does it show? | The item is the one ordered, arrived in acceptable condition, is installed and safe, and works to the manufacturer's specification in this location | The examination meets the performance needed for its intended use, such as precision, trueness and measuring interval |
| Typical evidence | Installation report, functional and safety checks, software versions, interface test, documents received | Precision, comparison, linearity, detection, interference and reference-interval studies against predefined criteria |
| When? | Before the equipment is used for anything, and again after a repair, move or major change | After acceptance, before patient results are reported for each examination |
| Outcome | Equipment status (for example, in service for method evaluation) | Authorisation to report patient results for a defined examination and scope |
| ISO 15189:2022 | Clauses 6.4.3 and 6.4.7 | Clauses 7.3.2 and 7.3.3 |
The two can share data, but one never replaces the other:
- A photometer check that passes says nothing about whether a creatinine method meets its precision claim.
- A creatinine verification that passes does not show that the analyser's electrical safety was tested.
The practical consequence is about status
CLSI EP10-Ed4 makes the same point from the method side: installation and the manufacturer's training should be complete, and operators familiar with the instrument, before an evaluation protocol starts (Chapter 5 of EP10).
The same steps under other names: IQ, OQ and PQ
Many laboratories, suppliers and assessors describe equipment acceptance in the language of qualification. CLSI QMS13 divides it into:
| Step (QMS13) | What it confirms | Usually done by | Where it sits in this course |
|---|---|---|---|
| Installation qualification (IQ) | What was delivered matches the order and has been set up correctly in a suitable environment | The manufacturer's engineer (QMS23) | The acceptance testing of this chapter (criteria A-2 to A-8 in Worked Example 0.1) |
| Operational qualification (OQ) | It operates to the manufacturer's specifications, interfaces included | The manufacturer's engineer (QMS23) | |
| Performance qualification (PQ) | It performs as the laboratory needs under normal working conditions | Laboratory staff | The method studies QMS13 puts inside PQ (precision, trueness, linearity, method comparison, reference intervals) are the verification of Chapters 5 to 20, kept as a separate decision for each examination |
QMS13 calls the whole set equipment validation (§6.1–6.3). CLSI QMS23 adds that IQ and OQ are usually carried out by the manufacturer's engineer, and that the laboratory keeps their records with the equipment documentation (§1.1).
The two vocabularies describe the same work, divided in different places. Use whichever vocabulary your own procedures use, but make sure each record says which step it covers.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, §0.2 Accept it for service (Equipment acceptance is not method verification; The same steps under other names), pp.7–9
0.3 Maintain it and record changes: the five kinds of entry
Once the analyser is in service, its record grows with every event that could affect results. Five kinds of entry make up most of it.
| Kind of entry | What the record must show | ISO 15189:2022 |
|---|---|---|
| 1. Preventive maintenance | The programme comes from the manufacturer's instructions. Record what was done, when and by whom. If the laboratory departs from the manufacturer's schedule (for example changing a part less often), record the deviation and its reason. | 6.4.5; 8.4.1 |
| 2. Service visits | Reason for the visit, what was found, what was done, parts replaced, any software change and the checks performed before the engineer left. The service report is filed or linked; the laboratory's own entry says what the laboratory checked afterwards and who decided the instrument could be used again. | 6.4.5 |
| 3. Faults and repairs | What happened, when it was noticed, which results might be affected and what was done. | 6.4.5; 6.4.6; 7.5 |
| 4. Modifications | Software and firmware upgrades, new modules, changed settings and interface changes: the old and new versions or settings, the date and time of the change, who authorised it and what was checked afterwards. | — |
| 5. Calibration and verification records | Reports and certificates of calibration or verification of the equipment, with their dates, times and results. | 6.4.7 |
Service visits: safety for the engineer
The instrument is decontaminated before the engineer opens it, and the engineer is given suitable protective equipment, as the standard requires for service, repair and decommissioning (clause 6.4.5).
Faults and repairs: what happens to the instrument and to past results
Also → look at what the fault may have done to results already reported → handle affected results as nonconforming work (clause 7.5; Chapter 17)
Incidents attributable to the equipment itself → investigated and reported to the manufacturer or authorities as required; act on recalls and safety notices (6.4.6)
Calibration and verification records: what goes where
For a chemistry analyser these include the manufacturer's periodic performance checks, temperature and photometer checks, and the calibration certificates of any equipment used to check it, such as a reference thermometer.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, §0.3 Maintain it and record changes, pp.9–10
0.3 A change can trigger two reviews; return to service
🔥 KEY POINT: Every change entry ends with a decision on two questions.
Question 2 — Could the change affect any examination method? If so, which, and what evidence is needed?
The answer depends on what changed. Table 0.3 gives examples. The decisions in the right-hand columns are illustrative: each laboratory defines its own in its procedures, usually with the manufacturer's guidance on what each part or version change can affect.
| Change | Equipment review before use | Possible effect on methods, and the evidence to consider |
|---|---|---|
| Routine preventive maintenance as scheduled | Manufacturer's post-maintenance checks; QC acceptable | None expected; review only if QC shifts |
| Photometer lamp replaced | Manufacturer's photometer check; QC acceptable at all levels | All photometric examinations; a QC shift calls for investigation before reporting; a single-run repeatability check where the local procedure asks for one (Worked Example 6.3) |
| Sample probe replaced | Probe alignment and volume checks | Carryover where it matters (Chapter 12); QC |
| Software or firmware upgrade | Version recorded; release notes reviewed; interface retested where data transfer is involved | Any examination whose calculation, flags, measuring interval or dilution behaviour the release notes say has changed; verify the changed aspect (Chapters 9 and 16) |
| Major repair of a measuring module (for example an ion-selective electrode unit) | Return-to-service acceptance against the original criteria | Examinations on that module; QC and, where the plan requires, a patient-sample comparison (Chapter 16) |
| Relocation to another room or site | Repeat of installation and safety checks relevant to the move | QC; comparison with the previous results if the environment or services differ |
| Manufacturer's recall or safety notice | Actions in the notice; record of what was done | As the notice describes; review of results produced while the problem existed (Chapter 17) |
The value of the table is that the second question is asked every time.
Return to service is an acceptance decision in its own right
- ISO 15189:2022 asks for the same check against acceptability criteria before equipment is returned to service as before it was first placed in service. It notes that a calibration certificate for the returned item can, where relevant, provide the evidence (clause 6.4.3).
- QMS13 adds that a move, maintenance or a modification calls for the installation and operational checks to be repeated and compared with the original results (§6.2, 6.3.1).
- Write the return-to-service criteria into the maintenance procedure in advance, so that nobody has to invent them on the afternoon of a repair.
Worked Example 0.2 (study section 11) shows a return to service that ends with two examinations back in use and one still restricted.
Amending a record
Records are amended in a way that keeps the original visible. A corrected maintenance entry shows the original entry, the correction, who made it and when (clause 8.4.2).
| Medium | How the original stays visible |
|---|---|
| Electronic system | Audit trail |
| Paper | A single line through the original and a dated, initialled correction |
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, §0.3 Maintain it and record changes (A change can trigger two reviews), pp.10–12
0.4 Track its status and retain its history
Status that staff can see
At any moment, every item of equipment has a status, and staff must be able to see it at the instrument, in the equipment register and, where it matters, in the information system. The common set is:
| Status | Meaning | What else happens |
|---|---|---|
| In service | May be used for the purposes stated in the record | For a new analyser the stated purpose may be limited, for example to method evaluation, until each examination is authorised for patient testing |
| Out of service | Must not be used, usually because of a fault, maintenance or an overdue check | Clear label on the instrument; the information system stops accepting results from it where possible |
| Quarantined | Held apart while a question is investigated, for example after a suspected contamination, a dropped instrument or a doubtful repair | Not used until the investigation decides whether it returns to service, needs repair or is retired |
| Retired or obsolete | Permanently withdrawn | Labelled, removed from the register of active equipment and disconnected from the information system, but its record is kept |
The record should say who may change a status, and each change is dated, timed and signed like any other entry.
Records that outlive the instrument
The equipment record must be kept up to date and be easy to retrieve for the whole working life of the equipment, and longer where the laboratory's retention rules require it (clause 6.4.7). Clause 8.4.3 asks the laboratory to:
- set retention times for its records,
- protect them from loss and unauthorised change,
- back them up, and
- keep them retrievable and legible for the whole retention period, in whatever medium it uses.
The standard notes that retention times can be chosen in the light of identified risks, and that legal liability for some kinds of examination can justify keeping records much longer than usual.
Retirement: where records are most often lost
The instrument leaves, the service contract ends, and the folder goes into a cupboard or the electronic file is archived without an index. The retirement entry should say:
- where the full record now lives and how to retrieve it, and
- that data held only in the analyser or the supplier's systems were exported before the instrument was removed.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, §0.4 Track its status and retain its history, pp.12–13
Worked Example 0.1 (part 1): delivery, installation and a failed check
WORKED EXAMPLE 0.1 · A CHEMISTRY ANALYSER FROM DELIVERY TO ENTRY INTO SERVICEAll names, identifiers, dates, readings and documents in this example are synthetic. The manufacturer, model and supplier are fictitious. The acceptance criteria are illustrative local criteria, not recommendations for any laboratory or any real instrument. The analyser is the one called analyser 1 in Chapters 5 to 20.
Situation
The laboratory has bought a chemistry analyser to replace its current one. The plan for verifying the creatinine method has already been written (Chapter 5), but no study may start until the analyser has been accepted and entered into service.
Step 1 — Receive and identify (Day 1)
- The analyser arrived at 10:20.
- The receiving technologist checked the delivery against the purchase order and the packing list, confirmed that the transit indicators on both crates were intact, and photographed the crates before opening.
- The main unit, the ion-selective electrode module and the sample handler each carried a serial number, all recorded.
- One reagent tray cover listed on the packing list was missing.
- The analyser was given the laboratory ID CHEM-01, labelled, entered in the equipment register with the status received, not in service, and placed in its planned bay.
Step 2 — Install and test (Days 2 to 7)
- The manufacturer's engineer installed the analyser and worked through the installation protocol.
- On Day 3 the engineer upgraded the instrument software from version 3.2.0 to 3.2.1, the version named in the current instructions for use. The section scientist read the release notes, recorded both versions and noted that, as no patient or study results had yet been produced, no method review was needed.
- Hospital engineering carried out the electrical safety test.
- On Day 6 the laboratory ran its interface check: 20 test orders with known synthetic results, including high, low and flagged values, sent from the analyser to the laboratory information system.
| No. | Criterion, written before installation | Source | Evidence | Result |
|---|---|---|---|---|
| A-1 | Delivery complete against order and packing list; no transit damage | Laboratory | Delivery check, Day 1; photographs | Met, except one reagent tray cover missing (no effect on results; delivered Day 4) |
| A-2 | Room temperature and humidity within the manufacturer's operating range; water at the analyser inlet no more than 1.0 µS/cm | Manufacturer's site requirements (limits illustrative) | Readings, Day 2 | Met: 22.5 °C, 41% relative humidity; 0.3 µS/cm |
| A-3 | Electrical safety test passed | Hospital engineering | Certificate ES-2026-1184 (synthetic) | Met |
| A-4 | Every item of the manufacturer's installation checklist completed and passed, including reaction temperature 37.0 ± 0.1 °C and the photometer check at all wavelengths | Manufacturer | Installation report IR-0518, signed by the engineer, Day 5 | Met: 37.02 °C; photometer check passed at all 12 wavelengths |
| A-5 | Sample and reagent probe checks passed: alignment, volume and liquid-level detection | Manufacturer | Installation report IR-0518 | Met |
| A-6 | Installed software and firmware match the versions named in the current instructions for use | Laboratory | Version screen, printed and signed, Day 5 | Met (software 3.2.1 after the Day 3 upgrade) |
| A-7 | Interface: 20 test orders with known results transferred with correct values, units, flags and comments | Laboratory | Interface test log | Not met on Day 6 (19 of 20: urine creatinine transferred without its unit). Mapping corrected; retest on Day 7: 20 of 20. Met |
| A-8 | Emergency stop works; operators shown the safe handling and waste routes | Manufacturer; hospital safety procedure | Installation report IR-0518; training sign-off | Met |
Step 3 — Deal with the failed check (Days 6 and 7)
Criterion A-7 failed. The information system's mapping for urine creatinine had no unit attached, so the result would have reached a clinician as a bare number.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, Worked Example 0.1 A chemistry analyser from delivery to entry into service (Situation, Steps 1–3, Table 0.4), pp.13–16
Worked Example 0.1 (part 2): authorise, enter into service, record
WORKED EXAMPLE 0.1 · CONTINUEDStep 4 — Review and authorise (Day 8)
- The section scientist reviewed the evidence for each criterion against Table 0.4 and recommended acceptance.
- The laboratory director, who is authorised to accept analysers into service, reviewed the summary and signed the acceptance at 15:30.
- No condition remained open: the missing tray cover had arrived on Day 4.
Step 5 — Enter into service for a defined purpose (Day 9)
At 08:00 on Day 9 the status changed to in service: method evaluation and training only; no patient results.
| Field | Entry |
|---|---|
| Equipment ID | CHEM-01 (label fixed to the front panel) |
| Description | Clinical chemistry analyser with photometric and ion-selective electrode modules; called analyser 1 in this book |
| Manufacturer and model | Veltara Instruments, model VX-900 (fictitious) |
| Supplier and service contact | Northmere Diagnostics (fictitious); service line and contract number SC-7741 (synthetic) |
| Serial numbers | Main unit VX9-24-00518; ion-selective electrode module ISE-24-1137; sample handler SH-24-0402 |
| Software and firmware | Instrument software 3.2.1 (upgraded from 3.2.0 on Day 3, 14:05); photometer firmware 1.08; electrode module firmware 2.04; middleware 5.6; interface driver 2.1 |
| Location | Core laboratory, room B.14, bay 2 |
| Condition on receipt | New; transit indicators intact; one reagent tray cover missing, delivered Day 4 |
| Instructions for use | Operator's manual version 3.2 (May 2026), held in the document control system as EQ-CHEM-01-IFU; current copy also on the analyser's on-board help; maintenance procedure SOP-CHEM-014 |
| Documents received | Installation report IR-0518; electrical safety certificate ES-2026-1184; declaration of conformity; service contract SC-7741 |
| Received | Day 1, 10:20 (received by the receiving technologist; delivery check signed) |
| Acceptance testing | Days 2 to 7, against criteria A-1 to A-8 (Table 0.4), approved by the laboratory director before delivery |
| Evidence that criteria were met | Table 0.4 with the documents listed above; A-7 failed on Day 6 and met on Day 7 after correction |
| Acceptance decision | Accepted, no open conditions. Reviewed by the section scientist; authorised by the laboratory director, Day 8, 15:30 |
| Entered into service | Day 9, 08:00, for method evaluation and training only |
| Current status | In service: method evaluation and training only; no patient results |
| Operators | Two study operators and the section scientist trained by the manufacturer and signed off as authorised, Day 7 (training record TR-CHEM-01, synthetic) |
| Access to settings | Calibration factors, reportable ranges, rerun and dilution rules changeable only at supervisor level (section supervisor and section scientist); operators at routine level; access list printed and signed, Day 7 |
| Preventive maintenance programme | Daily, weekly and quarterly tasks as in the manufacturer's maintenance schedule, implemented in SOP-CHEM-014; no deviations from the manufacturer's schedule |
| Calibration and verification records | Manufacturer's performance checks: installation report IR-0518 (Day 5), then six-monthly service checks. Reference thermometer certificate: in the thermometer's own record. Assay calibrations and QC: held in the analyser and QC software, retained under the records procedure |
| Event log | Table 0.6 |
| Retention | For the life of the analyser and at least as long afterwards as the patient results produced on it are kept, or longer if national rules require (illustrative local rule; records procedure) |
| Record owner | Section supervisor, chemistry |
| Date and time | Event | By | Result or finding | Status after | Method review needed? |
|---|---|---|---|---|---|
| Day 1, 10:20 | Received and identified | Receiving technologist | Delivery checked; tray cover missing | Received, not in service | No (not in use) |
| Day 3, 14:05 | Software upgrade 3.2.0 to 3.2.1 by service engineer | Engineer; recorded by section scientist | Release notes reviewed | Received, not in service | No: no results produced yet |
| Day 4, 09:10 | Missing tray cover delivered and fitted | Receiving technologist | Complete against packing list | Received, not in service | No |
| Day 6, 16:40 | Interface test | Interface analyst | 19 of 20 correct; urine creatinine without unit | Received, not in service | No (not in use) |
| Day 7, 11:15 | Interface mapping corrected; full retest | Interface analyst | 20 of 20 correct | Received, not in service | No |
| Day 8, 15:30 | Acceptance authorised | Laboratory director | Criteria A-1 to A-8 met | Accepted | No |
| Day 9, 08:00 | Entered into service | Section supervisor | Label, register and information system updated | In service: method evaluation and training only | Not applicable |
What this example shows
- Each milestone has its own date and its own evidence, so a reader can see what was known when.
- The acceptance criteria were written and approved before delivery, so the interface failure was a finding that had to be fixed, not a judgement to be argued.
- The software upgrade during installation is recorded with both versions, so any later question about which version produced which result can be answered.
- The status says what the analyser may be used for: evaluation, not patient reporting. The verification of each examination is the next decision.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, Worked Example 0.1 (Steps 4–5, Tables 0.5 and 0.6, What this example shows), pp.16–19
Reusable equipment-record template
Illustrative layout; adapt the fields and wording to the laboratory's own procedures. You can copy this table into your own document.
| Field | Entry |
|---|---|
| Equipment ID | |
| Description and intended use in the laboratory | |
| Manufacturer and model | |
| Supplier and service contact; contract reference | |
| Serial numbers of the main unit and separately serialised modules | |
| Software, firmware, middleware and interface versions (with dates of any change) | |
| Location (and any later move, with date) | |
| Condition on receipt: new, used or reconditioned; damage or missing items | |
| Instructions for use: title, version, and where staff find the current copy | |
| Documents received | |
| Received: date, time, by whom | |
| Acceptance criteria: reference and who approved them, with date | |
| Acceptance testing: dates and evidence reviewed | |
| Acceptance decision: outcome, conditions, reviewed by, authorised by, date and time | |
| Entered into service: date, time and purpose (for example, method evaluation only) | |
| Current status: in service (purpose), out of service, quarantined, retired | |
| Operators trained and authorised: names and training record reference | |
| Access to settings: who may change calibration, ranges and rules, and where the access list is kept | |
| Preventive maintenance programme and any recorded deviation from the manufacturer's schedule | |
| Calibration and verification records: what, how often, where kept | |
| Event log reference | |
| Retention rule and where the record will be kept after retirement | |
| Record owner |
Event log columns
| Date and time | Event | By whom | Result or finding | Status after | Equipment re-acceptance needed | Method review needed |
|---|---|---|---|---|---|---|
| maintenance, service visit, fault, repair, modification, calibration or verification, move, status change | yes or no, with reason | which examinations, what evidence, who decided |
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, Reusable equipment-record template (Table 0.7 and event log columns), pp.20–21
Worked Example 0.2: returning a repaired module to service
WORKED EXAMPLE 0.2 · RETURN TO SERVICEAll identifiers, results and decisions in this example are synthetic. The return-to-service criteria and the comparison limits are illustrative local choices, not recommendations for any laboratory or instrument.
Situation
In month 4 of routine use, before analyser 2 is added in month 7, the ion-selective electrode module of CHEM-01 fails its daily slope check at 13:10. The engineer replaces the sodium and reference electrodes. The photometric examinations, creatinine included, do not use the module and are not affected. The emergency department asks for electrolytes to be back on CHEM-01 the same afternoon.
Step 1 — Set the status module by module
- The section scientist marks the electrode module out of service on the instrument, in the register and in the information system, so that no sodium, potassium or chloride result from CHEM-01 can be released.
- The photometric examinations stay in service.
- Electrolytes move to the back-up analyser kept after the changeover (Chapter 11), which has its own verification and QC.
- The emergency department is told by telephone which analyser is producing electrolytes and that results may take longer; the call is logged.
Step 2 — Apply the criteria written in advance
The maintenance procedure already contains return-to-service criteria for a repaired electrode module. Table 0.8 shows them beside the evidence.
| No. | Criterion, from the maintenance procedure | Evidence | Result |
|---|---|---|---|
| R-1 | Manufacturer's post-repair checks passed: electrode slopes within the manufacturer's range, no error flags | Service report SR-0731 (synthetic) | Met |
| R-2 | Both QC levels for sodium, potassium and chloride within limits, run twice at least an hour apart | QC record | Met at both runs |
| R-3 | Ten patient samples measured on CHEM-01 and on the back-up analyser: every sodium and chloride difference within ±3 mmol/L and every potassium difference within ±0.2 mmol/L | Comparison log | Sodium 10 of 10; chloride 10 of 10; potassium 9 of 10 (one difference +0.3 mmol/L, the first sample run after the repair) |
| R-4 | Software version, electrode lot numbers and settings recorded; no setting changed | Event log | Met |
Step 3 — Interpret
R-1, R-2 and R-4 are met. R-3 is met for sodium and chloride but not for potassium, because the criterion says every difference and one (+0.3 mmol/L) exceeds the ±0.2 mmol/L limit.
Step 4 — Decide, examination by examination
| Examination | Decision | What happened |
|---|---|---|
| Sodium and chloride | Proceed | Every criterion is met; the module returns to service for these two examinations at 17:40 |
| Potassium | Collect more data | The procedure allows one repeat of R-3, with ten new samples, when a single pair fails. The repeat is run the next morning: all ten potassium differences within ±0.2 mmol/L; potassium returns to service at 09:15 |
| Potassium, until then | Restrict | Potassium stays on the back-up analyser overnight. The middleware rule that routes potassium to CHEM-01 is switched off and the change is logged, so that the restriction is enforced by the system rather than by memory |
Step 5 — Record and tell
- The event log carries the fault, the repair, each status change with its time, the criteria, the evidence, the failed pair, the repeat and the decisions, each signed by the person authorised to make it.
- The emergency department and the night shift are told when sodium and chloride return to CHEM-01, and again when potassium follows.
- Results produced between the last passed slope check and the failure are reviewed as possible nonconforming work, which is a separate question from the return to service (clause 7.5; Chapter 17).
What this example shows
Because the criteria were written before the fault, the afternoon's discussion was about evidence, not about what counted as good enough. The decision was made per examination and came out three ways: proceed for two, collect more data for one, and a restriction enforced by the information system while the extra data were collected.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, Worked Example 0.2 Returning a repaired module to service (Table 0.8), pp.21–23
Common errors
Each error below is followed by the habit that prevents it.
| # | ⚠️ Common error | Why it is a problem / what to do instead |
|---|---|---|
| 1 | One date for everything | Recording only "installed" hides when the equipment was accepted, on what evidence, and from when it could be used. Keep receipt, acceptance and entry into service as three dated milestones. |
| 2 | The engineer's report as the decision | The report is evidence. The laboratory reviews it against its own criteria, and a named person decides. |
| 3 | Criteria written after the checks | A criterion chosen once the readings are known no longer tests anything. |
| 4 | Treating acceptance as verification | A passed installation shows that the instrument works to specification; it says nothing about whether an examination meets its claims for the laboratory's use. |
| 5 | Software changes recorded as "upgrade done" | Without the old and new versions, the time of the change and a recorded method review, a later investigation cannot tell which results were produced under which version. |
| 6 | Labels, register and information system out of step | A status change is complete only when all three agree. |
| 7 | Records lost at retirement | Data held in the analyser or the supplier's systems are exported, and the retirement entry says where the full record now lives. |
| 8 | Returning equipment to service on the engineer's word | Return to service is an acceptance decision against criteria written in advance, made by a named person, and examination by examination where a repair affects only part of the instrument. |
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, Common errors, p.23
Chapter 0 checklist and the next decision
Chapter 0 checklist
Before method verification starts, confirm that you can tick each item.
- ☐ The equipment has a unique laboratory ID, a label and an entry in the equipment register.
- ☐ Manufacturer, supplier, serial numbers, software and firmware versions, location and condition on receipt are recorded.
- ☐ The current instructions for use are identified by version, and staff know where to find them.
- ☐ Acceptance criteria were written and approved before installation, and the evidence for each is in the record.
- ☐ Any failed criterion was corrected and rechecked before acceptance, and the record shows both results.
- ☐ Receipt, acceptance and entry into service have separate dates, and the person who authorised acceptance is named.
- ☐ The status allows method evaluation and prevents patient reporting until each examination is authorised.
- ☐ Operators who will run the studies are trained and authorised on the instrument, access to settings is restricted, and the preventive maintenance programme is in place.
- ☐ The retention rule for the equipment record is stated.
From readiness to evaluation
The equipment record now shows that CHEM-01 is the analyser that was ordered, that it arrived in good condition, that it was installed and checked against criteria written in advance, and that a named person accepted it into service for evaluation. That is what readiness for evaluation means, and nothing more.
It does not show that the creatinine method on this analyser is precise enough, true enough or suitable for the patients the laboratory serves. As a supervisor, the author wants both on file before the analyser reports a patient result, and wants them kept apart, because they answer different questions and they will be reopened for different reasons.
Chapter 0 references (as cited by the book)
- International Organization for Standardization. ISO 15189:2022 Medical laboratories — Requirements for quality and competence. 4th ed. ISO; 2022 (December). Clauses 6.4.1–6.4.7 (equipment; 6.4.7, equipment records, is the main technical reference for this chapter), 7.5 (nonconforming work), 8.4.1–8.4.3 (creation, amendment and retention of records). Clauses 7.3.2 and 7.3.3 are cited for comparison in Table 0.2.
- Clinical and Laboratory Standards Institute. Preliminary Evaluation of Quantitative Medical Laboratory Measurement Procedures. 4th ed. CLSI guideline EP10-Ed4. CLSI; 2024. Chapter 5, Preparatory Procedures.
- Clinical and Laboratory Standards Institute. Quality Management System: Equipment. 1st ed. CLSI guideline QMS13-A. CLSI; 2011. Sections 5 (planning, selection qualification), 6.1–6.3 (installation, operational and performance qualification; reverification after a move, service or modification).
- Clinical and Laboratory Standards Institute. General Laboratory Equipment Performance Qualification, Use, and Maintenance. 2nd ed. CLSI guideline QMS23-Ed2. CLSI; 2019. Section 1.1 (scope; IQ and OQ records kept with the equipment documentation).
ISO and CLSI documents are cited for attribution and explained in the author's own words; consult the current editions for the full requirements and procedures.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, Chapter 0 checklist; From readiness to evaluation; Chapter 0 references, pp.24–25
Training course, not a certification. Based on the author's textbook; all examples use synthetic data. It does not replace the CLSI and ISO documents it cites, and it is not affiliated with or endorsed by CLSI or ISO.
© 2026 Hassan Shawki. Course text adapted from the author's textbook Clinical Laboratory Method Evaluation in Practice.
⚡ Last-Minute Review — Equipment Readiness and Records
Read these lists before you start any method evaluation. Then open Progress / Results to see your weak areas.
The decision
- Is the analyser identified, accepted and recorded, and ready for method evaluation?
- "Ready" from the engineer means power, water and software, not accepted, and not authorised for anything.
- Readiness for evaluation means: the item ordered · arrived in good condition · installed and checked against criteria written in advance · accepted into service for evaluation by a named person. Nothing more.
Identify on arrival (Table 0.1)
- Equipment = anything that can influence a result, including instrument and LIS software, middleware, sample transport, centrifuges, water units, pipettes (ISO 15189:2022, 6.4.1)
- Unique laboratory ID on a label + register entry (6.4.2); serial number links to the manufacturer
- Record: ID · manufacturer and supplier · serial numbers of main unit and modules · software/firmware/middleware/interface versions · location · condition on receipt · instructions for use (version + where kept) · documents received
- Two trouble spots: software (record both versions if upgraded during installation, with dates) and where the current instructions are kept (6.4.4)
Accept for service
- Three milestones, three dates: receipt → acceptance testing (ends with a review and decision) → entry into service (defined purpose, named person, never before the acceptance decision)
- Criteria written and approved before the checks; sources: manufacturer · hospital (electrical safety, site services) · laboratory (LIS transfer of results, units, flags)
- Write criteria that can be checked; state the number and the observed value, not only "pass"
- On file before signing: access levels · trained and authorised operators · safety checks (6.4.4, 6.4.5)
- Engineer's report = evidence; a named laboratory person decides; authority defined in advance
- Non-critical open item → condition with owner and deadline · failed criterion affecting results → stays out of service
Acceptance ≠ verification (Table 0.2)
- Acceptance judges the instrument (6.4.3, 6.4.7) · verification/validation judges each examination procedure (7.3.2, 7.3.3)
- Accepted analyser → in service for method evaluation and training, not patient reporting → patient reporting starts examination by examination (Chapter 20)
- IQ (installed as ordered, suitable environment) + OQ (operates to specification, interfaces included) = this chapter's acceptance testing · PQ (laboratory staff, normal working conditions) — QMS13 puts method studies inside PQ; this book keeps them as method verification
- "Validation" on an equipment report ≠ validation of an examination method
Maintain and record changes
- Five entries: preventive maintenance (deviation from schedule + reason) · service visits (decontaminate first; lab records its own checks and who decided) · faults and repairs (out of service + label; review reported results as nonconforming work, 7.5) · modifications (old/new version, date and time, who authorised, what was checked) · calibration/verification records
- Ticked but undated, unsigned checklist = not a record (8.4.1)
- After every change, two reviews: re-accept the equipment? · which examination methods, what evidence?
- "Upgrade done, QC in range" can hide a changed dilution rule or reportable range that two-level QC never detects
- Return to service = an acceptance decision against criteria written in advance (6.4.3); QMS13: repeat IQ/OQ checks after a move, maintenance or modification and compare with the original
- Amendments keep the original visible (audit trail; single line + dated initials) (8.4.2)
Status and retention
- Statuses: in service (for a stated purpose) · out of service · quarantined · retired/obsolete (record kept)
- Label, register and information system must agree; the record says who may change a status
- Keep the equipment record for the working life and beyond (6.4.7, 8.4.3); sensible local rule: at least as long as the patient results produced on it
- At retirement: export data held in the analyser or supplier systems; say where the full record lives
Worked examples in one line each
- WE 0.1 (CHEM-01): Day 1 received (tray cover missing) · Day 3 software 3.2.0 → 3.2.1 recorded · A-7 interface 19/20 on Day 6 → mapping fixed, all 20 resent → 20/20 Day 7 · Day 8 director authorises · Day 9 in service for method evaluation and training only
- WE 0.2 (electrode module): module out of service, photometric tests stay in service · R-3 potassium 9/10 (one +0.3 vs ±0.2 mmol/L) → pair not excluded · sodium and chloride proceed (17:40) · potassium: one repeat of ten new samples → 10/10, back at 09:15 · restriction enforced by middleware · past results reviewed separately as possible nonconforming work
Common errors
- One date for everything · engineer's report as the decision · criteria after the checks · acceptance treated as verification · "upgrade done" · labels/register/LIS out of step · records lost at retirement · return to service on the engineer's word
Key terms (book glossary)
- Acceptance testing (equipment): the checks of a new, moved or repaired item of equipment against criteria written before the checks start, ending in a recorded decision by a named person. It concerns the instrument, not the examination methods that run on it.
- Acceptance criterion: a rule, written before the study, that turns a result into a decision: meets, does not meet, or needs more evidence.
- Entry into service: the date and time from which equipment may be used for a stated purpose (for example, method evaluation only), authorised by a named person after the acceptance decision.
- Equipment record: the record kept for every item of equipment that could affect results: its identity, versions, acceptance, maintenance, faults, changes, status and history, kept for its working life and beyond as the retention rules require.
- Installation, operational and performance qualification (IQ, OQ, PQ): names used in CLSI QMS13 and by many suppliers for the stages of equipment acceptance: installation as ordered and in a suitable environment, operation to the manufacturer's specifications, and performance for the laboratory's needs. QMS13 places method studies inside PQ; this book treats them as method verification.
- Quarantined (equipment status): held apart and not used while a question about the equipment is investigated; the investigation decides whether it returns to service, is repaired or is retired.
- Return to service: an acceptance decision after a repair, move or other change, against criteria written in advance; it can be made examination by examination when a change affects only part of the equipment.
- Nonconforming work: any work, or result, that does not meet the laboratory's procedures, specifications or user requirements.
Training course, not a certification. Based on the author's textbook; all examples use synthetic data. It does not replace the CLSI and ISO documents it cites, and it is not affiliated with or endorsed by CLSI or ISO.
Source: Clinical Laboratory Method Evaluation in Practice (Shawki, 1st ed. 2026), Ch.0, pp.3–25; Glossary, pp.411–419